|   | 
     
       The 
        Owner's Duties in Construction, 
        Continued 
         
      <<<BACK 
        TO DESIGN DUTIES<<<  
        
      CONSTRUCTION 
        PHASE  
      
        - Execution 
          of the construction contract. Before work can begin, the contract 
          with the constructor must be executed. In addition, the constructor 
          should provide his bonds and evidence of insurance before mobilizing 
          on the site. 
 
       
      
        - Approval 
          of the construction schedule. The constructor should provide a comprehensive 
          construction schedule soon after execution of the contract. It is the 
          owner's responsibility to not only review and approve the schedule, 
          but also to monitor the schedule during construction, require periodic 
          updates from the constructor, and to put the constructor on notice if 
          the work falls behind schedule. 
 
       
      
        - Reconciliation 
          of allowances. In order not to impede the progress of the work, 
          the owner must finalize the scope of work for each cost allowance and 
          provide a change order to the constructor reconciling each allowance 
          as quickly as possible.
 
       
      
        - Inspection 
          and testing of the work. The architects and engineers have limited 
          responsibility to inspect and approve the work as its being completed. 
          It is the owner's responsibility to continuously and comprehensively 
          inspect the work to insure compliance with the contract documents. Outside 
          testing firms must be retained by the owner to provide certain quality 
          assurance work not normally provided by the constructor.
 
       
      
        - Project 
          safety. The owner is responsible to insure that the constructor 
          has a safety plan in place at the site.
 
       
      
        - Approval 
          of changes. architects do not warrant that their plans will be perfect. 
          Conflicts in the plans may arise which will require change orders to 
          the construction contract. It is the owner's responsibility to provide 
          these change orders and to fund the cost of the changes. In addition, 
          the owner's program may change during the construction, which may effect 
          the design. Prompt preparation and execution of change orders is necessary 
          to keep the project on schedule.
 
       
      
        - Approval 
          of colors and products. The architect will ask the owner to make 
          final decisions on colors, materials, and other design matters. 
 
       
      
        - Monitoring 
          subcontractors' and suppliers' payments. In order to protect himself, 
          and to protect his rights under the constructor's bonds, the owner must 
          have a program that enables him to insure that all subcontractors and 
          suppliers are being paid in a timely manner by the constructor. 
 
       
      
        - Resolution 
          of disputes. Differences of opinion will occur from time-to-time 
          on every project. It is the owner's responsibility, and to his benefit, 
          to resolve them quickly.
 
       
      
        - Adjustment 
          and administration of property insurance claims. In the event that 
          the project suffers a casualty loss covered by property insurance, sometimes 
          referred to as "builder's risk insurance", then it is the owner's responsibility 
          to promptly administer the adjustment of the claim on behalf of all 
          the covered parties.
 
       
      
        - Procurement 
          and installation of F.F.&E. As stated above, this function must 
          be administered in a timely manner by the owner, if the final product 
          is to be functional.
 
       
      
        - Development 
          of an operations and maintenance staff. Upon substantial completion 
          of the project, the constructor will turn over to the owner the responsibility 
          for operating and maintaining the facility. The owner needs to have 
          a staff in place prior to this event.
 
       
      
        - Coordination 
          of separate contractors. Sometimes the owner decides to have more 
          than one prime contractor involved in the project. Specialty contractors 
          are a good example, such as kitchen equipment contractors or data processing 
          contractors. It is the owner's responsibility, not the constructor's, 
          to coordinate the various prime contractors on the site.
 
       
      
        - Conduct 
          project meetings. A system of periodic management meetings needs 
          to be established at both the staff and executive levels. Agendas and 
          minutes need to be prepared by the owner for these meetings, if they 
          are to have value.
 
       
      
        - Acceptance 
          of the work. Once the work is completed, only the owner has the 
          authority to accept it from the constructor.
 
       
      
        - Establishment 
          of a warranty program. Since the owner is the beneficiary of the 
          construction and manufacturers' warranties, the owner must set up a 
          program to manage and administer these warranties.
 
       
      
        - Provide 
          continuing architectural and engineering (AE) services. During the 
          construction phase, certain AE services will be required. These include 
          certification of the constructor's pay requisition and approval of shop 
          drawings and submittals. Failure of the owner to provide these services 
          on a timely basis is a common root of constructors' claims against owners.
 
       
      >>>POST-CONSTRUCTION 
        DUTIES>>> 
       |